Question

If it takes a supplier 25 days to deliver an order once it has been placed and the standard deviation of daily demand is 20, which of the following is the standard deviation of usage during lead time?
A. 50
B. 100
C. 400
D. 1,000
E. 1,600

Answer

This answer is hidden. It contains 1 characters.