Question

If job 5 takes 3, 4 or 5 hours to be completed by workers A, B, and C, respectively, what would the row values for job 5 be after performing Step 1A of the assignment method?

A) 3, 4, 5

B) 8, 9, 10

C) 0, 1, 2

D) 6, 7, 8

E) 1, 4/3, 5/3

Answer

This answer is hidden. It contains 25 characters.