If the pessimistic duration of an activity is 10 and the optimistic duration is 4, what is the variance for the activity time when using CPM analysis?
A. 1
B. 2.333
C. 4.777
D. 10.4
E. 12

Answer

This answer is hidden. It contains 1 characters.