Question

If you have an optimistic time of 4 weeks, a most likely time of 6 weeks and a pessimistic time of 14 weeks on an activity in a CPM managed project, what is the expected time for this activity?
A. 4 weeks
B. 5 weeks
C. 6 weeks
D. 7 weeks
E. 8 weeks