Question

In MRP record calculations, the appearance of a negative value for the gross requirements of an end item in a specific time bucket

A) signals the need to purchase that end item in that period

B) implies that value was scheduled by the MPS

C) signals the need for a negative planned order receipt in that period

D) is impossible

E) All of the above are true.