Question

In MRP, system nervousness is caused by:

A) management's attempt to continually respond to minor changes in production requirements.

B) the use of the lot-for-lot approach.

C) management's marking part of the master production schedule as "not to be rescheduled".

D) the use of phantom bills of material.

E) management's attempt to evaluate alternative plans before making a decision.