Question

In setting up a kanban control system and you need to determine the number of kanban card sets needed. If the expected demand during lead time is 50 per hour, the safety stock is 20% of the demand during lead time, the container size is 4. If the lead time to replenish an order is 2 hours, what number of kanban card sets is needed?