Question

In setting up a kanban control system you need to determine the number of kanban card sets needed. If the expected demand during lead time is 24 per hour, safety stock is 10% of the demand during lead time, the container size is 5. If the lead time to replenish an order is 5 hours, what number of kanban card sets is needed?

Answer

This answer is hidden. It contains 8 characters.