Question

In the context of sequencing, the earliest due date (EDD) rule:

a. minimizes the maximum jobs past due.

b. maximizes average flow time of jobs past due.

c. maximizes resource utilization of jobs past due.

d. minimizes the average processing time of jobs past due.

Answer

This answer is hidden. It contains 1 characters.