Question

In the context of the Project Evaluation and Review Technique (PERT), which of the following is true of the beta probability distribution approach?

a. It allows managers to identify the best case, worst case, and most likely case for activity times.

b. It describes the inherent similarity in the optimistic, most probable, and pessimistic time estimates.

c. It is rigid in characterizing the distribution of times.

d. It forces activity times to a symmetric normal probability distribution.

Answer

This answer is hidden. It contains 1 characters.