In the development phase of the project life cycle:
a. the project team creates more detailed project plans, a more accurate cost estimate, and a more thorough WBS.
b. the project team delivers the required
work, and provides performance reports to stakeholders.
c. managers develop a business case, which describes the need for the project and basic underlying concepts.
d. managers prepare a preliminary or rough cost estimate for the required work.

Answer