Question

In translating construction cost cash flows across time to arrive at the present certainty-equivalent value of the construction cost as of time zero, the opportunity cost of capital (OCC) that should be used as the discount rate is best described as follows:
a) Use the contract interest rate on the construction loan.
b) Use a rate equal to or only slightly above the riskfree interest rate.
c) Use the development phase OCC reflecting the leverage in the construction project.
d) Use the yield on long-term Government bonds.

Answer

This answer is hidden. It contains 60 characters.