Question

It is week 1 and there are currently 20 As in stock. The MPS calls for 300 As at the start of week 5. If there are scheduled receipts planned for week 3 and week 4 of 120 As each and A has a lead time of 1 week when and how large of an order should be placed to meet the requirement of 300 As?

A) Week 1, 300 A s

B) Week 1, 40 A s

C) Week 5, 40 A s

D) Week 4, 40 A s

E) Week 4, 300 A s

Answer

This answer is hidden. It contains 1 characters.