Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,500 of direct materials and used $4,000 of direct labor. The job was not finished by the end of the month, but needed an additional $3,000 of direct materials in October and additional direct labor of $6,500 to finish the job. The company applies overhead at the end of each month at a rate of 200% of the direct labor cost. What is the amount of job costs added to Work in Process Inventory during October?
A. $16,000
B. $22,500
C. $37,000
D. $26,500
E. $32,000