Question

Job X, which has a duration of four days, is due by the close of business on Friday, December 23. Without looking at the work already scheduled on X's required resource, the scheduler schedules X to be begun on the morning of Tuesday, December 20. This is an example of:

A. infinite scheduling.

B. finite scheduling.

C. forward scheduling.

D. backward scheduling.

E. prioritization.