Job X, which has a duration of four days, is due by the close of business on Friday, December 23. Without looking at the work already at X's required resource, the scheduler schedules X to be begun immediately and assumes that X will be done four days from now. This is an example of:

A. infinite scheduling.

B. finite scheduling.

C. forward scheduling.

D. backward scheduling.

E. prioritization.

Answer

This answer is hidden. It contains 88 characters.