Question

Johanna Reid, a campaign manager at a child rights organization, recently started working on an illiteracy project. During the project, she needs to motivate team members to attain their project milestones and direct them through different phases of the project. Which of the following kinds of functions will these tasks be covered under?

A) planning

B) organizing

C) scrutinizing

D) evaluating

E) leading