Question

Jones Corp. has ordered 50 computers from Smith Computers Inc. The computer specifications, colors and price are each clearly specified in the contract, however the delivery date and place of delivery are not mentioned.
A.This contact will be unenforceable because it is too vague.
B.Because of the missing terms, performance will be excused due to commercial impracticality.
C.Because of the missing terms, performance will be excused due to impossibility of performance.
D.The courts can use UCC gap fillers to fill in the missing terms.