Question

Montaigne Corp. has the following information about its standards and production activity for November. The controllable variance is:


Actual total factory overhead incurred $28,175
Standard factory overhead:
Variable overhead . $3.10 per unit produced
Fixed overhead
($12,000/6,000 estimated units to be produced) $2 per unit
Actual units produced .. 4,800 units

A. $1,295U.
B. $1,295F.
C. $2,400U.
D. $2,400F.
E. $3,695U.

Answer

This answer is hidden. It contains 189 characters.