Question

Mr. Green contracts with Mr. Brown to repair his roof. Mr. Brown is about 75% done when the deadline of the contract occurs. Which legal standard would prevent Mr. Brown from being considered to be in breach of his agreement with Mr. Green?

A. Substantial performance standard

B. Strict performance standard

C. Reasonable person standard

D. Egg shell person standard

Answer

This answer is hidden. It contains 109 characters.