Question

Osprey Fabrication has the following aggregate demand requirements and other data for the upcoming four quarters.


Quarter Demand Previous quarter's output 1300 units
1 1400 Beginning inventory 0 units
2 1200 Stockout cost $50 per unit
3 1600 Inventory holding cost $10 per unit at end of quarter
4 1500 Hiring workers $40 per unit
Laying off workers $80 per unit
Subcontracting cost $60 per unit
Unit cost $30 per unit
Overtime $15 extra per unit

Which of the following production plans is better: Plan Achase demand by hiring and layoffs; Plan Bpure level strategy, or Plan C1350 level with the remainder by subcontracting?