Question


(p. 145) A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented below:



Using CPM, which activities make up the critical path?

A. A, B, D, F, G

B. A, C, E, F, G

C. A, C, B, F, E

D. A, D, E

E. None of the above