(p. 145) A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented below:



Using CPM, what is the Latest Finish Time for the last activity in this project (i.e., the total time to complete the project)?

A. 9 days

B. 10 days

C. 11 days

D. 12 days

E. 13 days