(p. 145) A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented below:



Using CPM, which activities have slack in this project?

A. A, B, C

B. B, D

C. Only C

D. C, E

E. F, G

Answer