Question


(p. 370) A company wants to determine its reorder point (R). Demand is variable and they want to build a safety stock into R. If the average daily demand is 12, the lead time is 5 days, the desired "z" value is 1.96, and the standard deviation of usage during lead time is 3, which of the following is the desired value of R?

A. About 6

B. About 16

C. About 61

D. About 66

E. About 79

Answer

This answer is hidden. It contains 157 characters.