Question


(p. 416) In setting up a Kanban control system you need to determine the number of Kanban card sets needed. If the expected demand during lead time is 25 per hour, the safety stock is 20% of the demand during lead time, the container size is 5, and the lead time to replenish an order is 5 hours, what is the number of Kanban card sets needed?

A. 5

B. 20

C. 27

D. 30

E. 34