(p. 416) In setting up a Kanban control system you need to determine the number of Kanban card sets needed. If the expected demand during lead time is 50 per hour, the safety stock is 20% of the demand during lead time, the container size is 4. If the lead time to replenish an order is 8 hours, what number of Kanban card sets is needed?

A. 60

B. 80

C. 90

D. 120

E. 150