(p. 38) The total output from a production system in one day is 900 units and the total labor necessary to produce the 900 units is 900 hours. Using the appropriate productivity measure, what is the resulting productivity ratio?

A. 1.000

B. 1.428

C. 0.700

D. 0.411

E. None of the above