Question


(p. 186) Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the eight tasks that make up the job are 7, 4, 7, 8, 9, 4, 3 and 6 minutes, and the cycle time is 8 minutes?

A. 3

B. 5

C. 6

D. 8

E. None of the above

Answer

This answer is hidden. It contains 40 characters.