Question


(p. 145) You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below.



The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be $100. If you crash this project by one day what is the total (i.e., direct and indirect) project cost?

A. $2,150

B. $2,300

C. $2,400

D. $2,450

E. $2,500

Answer

This answer is hidden. It contains 552 characters.