(p. 153) You have the following time and cost information below for use in a Time-Cost CPM Scheduling model.



What are the three costs per unit of time to expedite each activity?

A. A=$300, B=$200, C=$300

B. A=$100, B=$200, C=$400

C. A=$200, B=$200, C=$200

D. A=$100, B=$400, C=$300

E. A=$200, B=$300, C=$400