Question

Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. Given the project table below calculate the crash cost for 8 hours of time-savings. Suppose Pirmin calls the customer and asks for a project extension, reducing the amount of time he needs to crash. Calculate both the maximum time-savings available on a $25 crash budget and the cost to crash four hours of savings.


Activity Normal Duration (hours) Normal Cost ($) Crash Duration (hours) Crash Cost (S) Immediate Predecessors
A 2 10 2 0 None
B 3 15 2 23 A
C 5 25 4 30 B
D 3 20 1 24 C
E 6 30 4 45 C
F 1 5 1 0 C,E
G 7 35 6 50 F
H 10 50 7 80 D,G

Answer

This answer is hidden. It contains 768 characters.