Question

Poole Contractors makes a contract with Delta Resources to pay $50,000 for the supply of 500 truckloads of sand within a week. Delta Resources delivers the sand in two days after the contract was made. Poole Contractors pays the $50,000 promised in the contract. This is an instance of ________.
A) substantial performance
B) a material breach
C) a minor breach
D) strict performance