Question

Price Company's flexible budget shows $10,710 of overhead at 75% of capacity, which was the operating level achieved during May. However, the company applied overhead to production during May at a rate of $2.00 per direct labor hour based on a budgeted operating level of 6,120 direct labor hours (90% of capacity). If overhead actually incurred was $11,183 during May, the controllable variance for the month was:
A. $ 473 unfavorable.
B. $ 473 favorable.
C. $1,530 favorable.
D. $1,530 unfavorable.
E. $1,057 favorable.

Answer

This answer is hidden. It contains 112 characters.