Question

Process A has fixed costs of $1000 and variable costs of $5 per unit. Process B has fixed costs of $500 and variable costs of $15 per unit. What is the crossover point between process A and process B?

A) 50 units

B) 200 units

C) $2,500

D) $5,000

E) $9,500

Answer

This answer is hidden. It contains 23 characters.