Question

Projects A and B are mutually exclusive and have normal cash flows. Project A has an IRR of 15% and B's IRR is 20%. The companys WACC is 12%, and at that rate Project A has the higher NPV. Which of the following statements is CORRECT?

a. The crossover rate for the two projects must be less than 12%.

b. Assuming the timing pattern of the two projects cash flows is the same, Project B probably has a higher cost (and larger scale).

c. Assuming the two projects have the same scale, Project B probably has a faster payback than Project A.

d. The crossover rate for the two projects must be 12%.

e. Since B has the higher IRR, then it must also have the higher NPV if the crossover rate is less than the WACC of 12%.

Answer

This answer is hidden. It contains 527 characters.