Question

Pure Oil Company enters into a contract with QuikBilt, Inc., to construct an oil pipeline to withstand specific conditions. If QuikBilt fails to meet this standard, which is construed as a breach of contract and a breach of a duty of care, Pure might be awarded punitive damages to
a. establish, as a matter of principle, that QuikBilt acted wrongfully.
b. provide Pure with funds for a foreseeable loss beyond the contract.
c. provide Pure with funds for its loss of the bargain.
d. punish QuikBilt and deter others from similar acts.

Answer

This answer is hidden. It contains 1 characters.