Rose is in charge of advertising a new product launched by her company. She has defined the advertising for this product as an individual project that consists of seven activities. Following are the characteristics of these activities:

ActivityImmediate Predecessor(s)Activity Time(in weeks)
ANone2
BNone2
CA4
DB5
EC5
FD2
GE, F2

Calculate the earliest completion time for the project using a Gantt chart.

a. 10 weeks

b. 11 weeks

c. 12 weeks

d. 13 weeks

Answer

This answer is hidden. It contains 1 characters.