Question

Sanchez Company's output for the current period was assigned a $400,000 standard direct labor cost. The direct labor variances included a $10,000 unfavorable direct labor rate variance and a $4,000 favorable direct labor efficiency variance. What is the actual total direct labor cost for the current period?
A.$414,000.
B.$386,000.
C.$394,000.
D.$406,000.
E.$410,000.

Answer

This answer is hidden. It contains 140 characters.