Question

Station Task Time (minutes) Time left (minutes) Ready tasks (#followers)
A(4),B(4),D(1),E(2)
1 A 4 4.6 B(4),D(1),E(2)
B 0.8 3.8 D(1),E(2),C(3)
C 0.4 3.4 D(1),E(2),F(2)
E 0.4 3. D(1),F(2)
F 2.1 0.9 D(1),G(1)
2 D 1.8 4.2 G(1)
G 2. 2.2 H(0)
H 1.2 1.
Summary Statistics
Cycle time 6 minutes
Time allocated (cycle time * #) 12 minutes/cycle
Time needed(sum of task times) 10.1 minutes/unit
Idle time (allocated-needed) 1.900001 minutes/cycle
Efficiency (needed/allocated) 84.16666%
Balance Delay (1-efficiency) 15.83334%
Min (theoretical) # of stations 2

Key Term: Assembly-line balancing

44) A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of this process are listed below.


Task Duration (hours) Predecessor 1 Predecessor 2 Predecessor 4
A 4 --
B 6 --
C 2 A
D 6 A
E 3 B C
F 3 B C
G 5 D E F
H 1 G

a. Draw the appropriate network for this project.

b. What would the cycle time be if the goal is to produce 20 units per month (the plant operates

160 hours per month)?

c. What is the theoretical minimum number of workstations needed?

d. Balance with the most following tasks heuristic. What tasks are assigned to which stations?

e. What is the efficiency of the line obtained in part d?

Answer:

Answer

This answer is hidden. It contains 0 characters.