Question

Station Task Time (minutes) Time left (minutes) Ready tasks (#followers)
A(6),E(3),F(3)
1 A 5 2.5 E(3),F(3),B(5)
B 0.7 1.8 E(3),F(3),C(4)
C 0.4 1.4. E(3),F(3),D(3)
E 0.3 1.1 F(3),D(3)
F 0.2 0.9 D(3),G(2)
D 0.3 0.6 G(2),H(2)
G 0.35 0.25 H(2)
2 H 0.4 2.6 I(1)
I 0.6 2. J(0)
J 0.3 1.7
Summary Statistics
Cycle time 3 minutes
Time allocated (cycle time * #) 6 minutes/cycle
Time needed (sum of task times) 4.05 minutes/unit
Idle time (allocated-needed) 1.95 minutes/cycle
Efficiency (needed/allocated) 67.5%
Balance Delay (1-efficiency) 32.5%
Min (theoretical) # of stations 2

Answer

This answer is hidden. It contains 0 characters.