Question

Suppose a project is subject to the following risk events (each with a given probability of occurring and a cost associated with that occurrence):



Given these, Event _____ should probably get the most attention and Event _____ should probably get the least.

A. II; IV

B. III; IV

C. I; III

D. I; II

E. II; III