Question

Suppose operation X feeds directly into operation Y. All of X's output goes to Y, and Y has no other operations feeding into it. X has a design capacity of 80 units per hour and an effective capacity of 72 units per hour. Y has a design capacity of 100 units per hour. What is Y's maximum possible utilization?

A. 80 percent

B. 72 percent

C. 90 percent

D. 70 percent

E. 60 percent

Answer

This answer is hidden. It contains 119 characters.