Question

Task Preceding Task Time to perform (min.)
A -- .69
B A .55
C B .92
D B .59
E B .70
F B 10
G C, D, E .75
H G, F .43
I H .29

(a) Draw a network diagram of precedence relationships.

(b) Compute the required cycle time per unit in minutes.

(c) Compute the theoretical minimum number of workstations required to produce 40 units per hour.

(d) Balance this line using the longest processing time heuristic.

(e) What is the efficiency of the line obtained in part d?