Question

Task Preceding Task Time to perform (min.)
A -- 40
B A 3.20
C -- 1.50
D B, C 2.80
E D 17.10
F E 12.80

a. Draw the network diagram of the precedence relationships.

b. Identify the absolute minimum and maximum cycle times.

c. How many workstations are required to meet the schedule?

d. What is the cycle time required to meet demand?

e. Balance this line using most following tasks heuristic.

f. What is the efficiency of the line obtained in part e?

g. Can the efficiency of this solution be improved? Explain.

Answer

This answer is hidden. It contains 553 characters.