Question

Task Preceding Task Time to perform (min.)
A -- 40
B A 3.20
C -- 1.50
D B, C 2.80
E D 17.10
F E 12.80

(a) Draw the network diagram of the precedence relationships.

(b) Identify the absolute minimum and maximum cycle times.

(c) What is the cycle time required to meet demand?

(d) What is the minimum number of workstations required to meet the schedule?

(e) Balance this line using the most following tasks heuristic.

(f) What is the efficiency of the line obtained in part (e)?

(g) Can the efficiency of this solution be improved? Explain.

Answer

This answer is hidden. It contains 513 characters.