Question

Task Predecessor(s) Duration (minutes)
A -- 4
B -- 0.8
C A, B 0.4
D -- 1.8
E -- 0.4
F C 2.1
G E, F 2.0
H D, G 1.2

a. Draw the precedence diagram.

b. Determine the desired cycle time.

c. Determine the theoretical minimum number of stations needed.

d. Balance this line using the most following tasks heuristic.

e. What is the efficiency of the line obtained in part d?

Answer

This answer is hidden. It contains 127 characters.