Question

Taylor is writing a progress report on the development of a new software program for a client. She and her team faced a technical glitch last week which has since been solved. Which of the following is the best way to present this information to the client?

A. "I'm really sorry, but we're running 2 days behind schedule. We will however be back on schedule by the end of the month."

B. "We have had a major problem last week because of which our work is affected to an extent. However, we should be able to finish by the due date."

C. "We overcame a major technical glitch last week. We are now on track to finish the work by the due date."

D. "Owing to the huge technical problem we faced last week, we are a little behind schedule. We may need an extension on the deadline"

E. "Please accept our sincere apologies. We will be unable to complete the work according to the estimated deadline."

Answer

This answer is hidden. It contains 217 characters.