Question

The activities, their respective immediate predecessors, and activity times for a particular project are given in the table below. Determine the earliest completion time for this project using a Gantt chart.

ActivityImmediate Predecessor(s)Activity Time(in weeks)
ANone1
BNone1
CA4
DB5
EC, D5
FE3
GF2

a. 14 weeks

b. 16 weeks

c. 18 weeks

d. 20 weeks