Question

The Baseline Project Plan does not:
A) contain all information collected and analyzed during project initiation and planning.
B) specify detailed project activities for the next life cycle phase, analysis, and less detail for subsequent project phases.
C) include being used by the project selection committee to help decide if the project should be accepted, redirected, or canceled.
D) reflect the best estimate of the project's scope, benefits, costs, risks, and resource requirements given the current understanding of the project.
E) include the database metadata.